Projects: Port Authority & Marine Work
| Project | Intermodal Transfer Facility |
| Owner | Port Authority of New York & New Jersey |
| Contractor | Conti Enterprises, Inc. |
| Location | Port Elizabeth, New Jersey |
| Description | Construction of concrete runways for gantry cranes including trench drains, railroad crossings and miscellaneous foundations. Approximately 180 tons of rebar and 700 tons of structural mesh were installed. |
| Project | Bayonne Bridge - Rehabilitation of the New Jersey Abutment |
| Owner | Port Authority of New York & New Jersey |
| Contractor | Spearin, Preston & Burrows, Inc. |
| Location | Bayonne, New Jersey |
| Description | Reconstruction of the New Jersey Abutment including 750 tons of stainless and epoxy steel rebar. |
| Project | Pier C Park |
| Owner | City of Hoboken |
| Contractor | EIC Associates, Inc. |
| Location | Hoboken, New Jersey |
| Description | Installation of 275 tons of pile cages and reinforcing beams and mat for nearly two acres of Park Deck, Pier and Promenade along the Hudson River Waterfront. |
| Project | Expressrail Corbin Street - Intermodal Rail Support Facility |
| Owner | Port Authority of New York & New Jersey |
| Contractor | Union Paving & Construction Co., Inc. |
| Location | Port Newark & Port Elizabeth |
| Description | Construction of two new bridges for the intermodal rail support facility. It spanned over tidal waters and included over 385 tons of rebar. |
| Project | Terminal B Roadway and Drainage Improvements |
| Owner | Port Authority of New York and New Jersey |
| Contractor | Conti Enterprises, Inc. |
| Location | Newark Liberty International Airport, Newark, New Jersey |
| Description | Over 500 tons of reinforcing steel was installed for the construction of new ramps, retaining walls, pumping stations, sign structures and high mast light towers for the Terminal B Roadway Improvement. |